MCQ Bank
To get the basic objective of developing a master production schedule, it must-----.
- A) Be outside from the inventory plan
- B) Satisfy customer demand
- C) Be separate from guidelines of the manufacturing plan
- D) Be outside the tactics of the production plan
A purchase order is represented in the material requirements planning (MRP) system by a:
- A) Neither a scheduled receipt nor a planned order
- B) Planned order
- C) Either a scheduled receipt or a planned order
- D) Scheduled receipt
Given following data in Order Promising Record of Master Production Schedule (MPS), how many units would be Available to Promise (ATP) in Week 5?
Week
2 3 4 5 6
Forecast 20 20 50 50 50
Orders 22 14 8 0 12
Available 68 48 58 68 18
Balance
ATP
MPS 60 0 60 60 0
On hand 30
Lot size = 60 units; Safety stock = 10, Lead Time = 0
- A) 68 units
- B) 18 units
- C) 48 units
- D) 56 units
Given following data in Order Promising Record of Master Production Schedule (MPS), how many units would be Available to Promise (ATP) in Week 6?
Week
3 4 5 6 7
Forecast 20 50 50 50 40
Orders 30 20 0 15 10
Available 20 30 40 50 10
Balance
ATP
MPS 0 60 60 60 0
On hand 50
Lot size = 60 units; Safety stock = 10, Lead Time = 0
- A) 75 units
- B) 35 units
- C) 50 units
- D) 45 units
The first step followed by the manager in the master production schedule is:
- A) Develop an initial MRP
- B) Checking the initial MRP against available capacity
- C) Resolve the difference between the initial MPS and available capacity
- D) Advance a rough-cut capacity plan
In the context of time fencing, what does the "frozen" segment (e.g., weeks 1–8) identify?
- A) Only the sales team can make changes in this period
- B) No changes are made except under extraordinary circumstances
- C) It allows for frequent and flexible changes to the schedule
- D) It is open for adjustment by logistics and planning teams
Given following data in Time-Phased Record of Master Production Schedule (MPS), what would be the MPS for Quarter 2?
Quarter
1 2 3 4
Forecast 30 60 70 40
Available Balance
MPS
On hand 40
Lot Size = 70 units; Safety Stock = 10 units; Lead Time = 0
- A) 20 units
- B) 70 units
- C) 30 units
- D) 0 units
In MRP, the precedent relationship shows:
- A) The order in which production steps must be accomplished
- B) Only the first step of the production process
- C) Only the final step of the production process
- D) The number of components required to produce an item
Given following data in Time-Phased Record of Master Production Schedule (MPS), what would be the projected Available Balance at the end of Week 4?
Week
1 2 3 4
Forecast 60 50 70 80
Available Balance
MPS 100 0 100 100
On hand 40
Lot Size = 100 units; Safety Stock = 20 units; Lead Time = 0
- A) 60 units
- B) 100 units
- C) 20 units
- D) 80 units
The master production schedule (MPS) is not an input to MRP systems
- A) False
- B) True
- C)
- D)
Backward Scheduling does not:
- A) Use MRP logic
- B) Schedule previous operations back from the last operation
- C) Schedule last operation to be complete on the due date
- D) Increase the inventory
Advantage of Time Phased Order Point (TPOP) over Reorder Point (Q, R) is that:
- A) TPOP shows Random shipment data
- B) TPOP shows Planned shipment data
- C) TPOP shows Variable shipment data
- D) TPOP shows Constant shipment data
A product has two operations in production and order is divided into 2 batches for operations overlapping. If the second operation is faster than the first, the first transfer batch should be:
- A) Batch size is independent of operations
- B) Smaller than the second
- C) Equal to the second
- D) Larger than the second
Distribution requirements planning (DRP) provides a link between:
- A) All of the given options
- B) Material requirements planning (MRP) and customer relationship management (CRM)
- C) Master production scheduling (MPS) and material requirements planning (MRP)
- D) Internal and external manufacturing planning and control (MPC) systems
The prime objective of production activity control (PAC) is:
- A) Meeting MPC plans
- B) Efficient use of labor
- C) Efficient use of capacity
- D) Efficient use of materials
In following Distribution Requirements Planning (DRP) record, what would be the available balance in period 3 if actual demand in period 1 is 16.
Period 1 2 3 4
Forecast 20 20 20 20
In transit 40
Projected 6| 26 6 26 6
available balance
Planned receipts 40
Planned shipments 40 40
Safety stock = 6; shipping quantity = 40; lead time = 1
- A) 40
- B) 30
- C) 20
- D) 26
With Reference to Production Activity Control (PAC), Just in time (JIT) approach assumes only two kinds of inventories, raw materials and
- A) Work in process
- B) Goods in transit
- C) Finished goods
- D) Semi-finished goods
Which of the following is not included in Item Master File prepared for Production Activity Control (PAC)?
- A) Part description
- B) Lot size quantity
- C) Manufacturing lead time
- D) Bill of material
In Distribution Requirement Planning (DRP), it is possible to use safety lead time when the uncertainty is more likely to be in terms of:
- A) Quantity
- B) Timing
- C) Quality
- D) Location
Bottleneck work centers limit the overall _____ of a plant.
- A) Machine quality
- B) Output
- C) Product range
- D) Capacity