To select a process model that is suitable to a project, the following criteria can be Considered except:
- A) Business goals of the organization
- B) Client and project requirements
- C) Expected size of the project
- D) Number of test cases required
Application of ___________ techniques helps the software designer to achieve high quality specification.
- A) Quality Management
- B) Testing
- C) Formal Technical Reviews
- D) Software Engineering
Making needed information available to project stakeholders in a timely manner. Choose suitable name of this activity.
- A) Information Distribution
- B) Source Selection
- C) Contract Administration
- D) Solicitation
In planning process tasks, schedule development phase includes _______________.
- A) When a certain report is required
- B) Time frame regarding provision of the input
- C) All of the given
- D) Different resources are going to be employed at various stages of the developments
Project goal _____________.
- A) May be clearly defined
- B) Must be ambiguous
- C) Definition does not matter
- D) Must be clearly defined
Developing individual and group skills/competencies to enhance project performance. Choose suitable name of this activity.
- A) Information Distribution
- B) Quality Assurance
- C) Team Development
- D) Project Plan Execution
The ___________ in project management process focuses on Change associated with error correction, adaptations required as the software's enviornment evolves, and changes due to enhancements which brought about by changing customer requirements.
- A) Analysis Phase
- B) Support Phase
- C) Development Phase
- D) Definition Phase
__________ is identifying the specific activities that must be performed to produce the various project deliverables
- A) Activity Duration Estimating
- B) Scope Planning
- C) Scope Definition
- D) Activity Definition
The _________________causes, as a "blocking state".
- A) Waterfall model
- B) Prototyping model
- C) Spiral model
- D) RAD model
The ___________ is a model that works on an iterative cycle of gathering customer requirements.
- A) RAD Model
- B) Prototyping Model
- C) Water Fall Model
- D) Incremental Model
The amount of time available for project development is always_____________.
- A) Unlimited
- B) Infinite
- C) Unpredictable
- D) Finite
In planning process tasks, need some new technology, hardware requirements arise, required a tool, arrange training of that newly acquired tool and need some other material. These all things comes under ___________.
- A) Staff acquisition
- B) Procurement planning
- C) Communication planning
- D) Project development plan
To expand or contract project scope, to modify cost, or schedule estimates are examples of __________
- A) Change request
- B) Change scope
- C) Change schedule
- D) Work results
The ____________________ does not support the development of a working model.
- A) Prototyping model
- B) RAD model
- C) Spiral model
- D) Waterfall model
Reviews conducted at each of this phase/s_______
- A) All of given
- B) Design
- C) Coding
- D) Analysis
________ ensures that the standards laid down for a project are followed.
- A) Quality assurance
- B) Quality control
- C) Process control
- D) Product evaluation
The answer of _____________ question help the team to establish a project schedule by identifying key project tasks and the milestones that are required by the customer.
- A) What will be done, by when?
- B) Where they are organizationally located?
- C) Who is responsible for a function?
- D) How will the job be done technically and managerially?
In planning process tasks, _____________ cannot be fixed and cannot be determined in the beginning.
- A) Scope factor
- B) Owner factor
- C) Cost factor
- D) Vendor factor
________________is anything that reduces the probability of potential consequences of project risk events.
- A) Preventive action
- B) Configuration plan
- C) Scope plan
- D) Corrective action
_________ defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address.
- A) Initial Process
- B) Executing Process
- C) Planning Process
- D) Controlling Process