MCQ Bank
A program plan measures which of the following?
- A) Performance
- B) Manpower
- C) Program requirements
- D) Facility requirements
If the total slack time available for the project begins to decrease from one reporting period to the next that may indicate that
- A) Work is taking longer than anticipated
- B) Both a and b
- C) None of the above
- D) More highly skilled labor is required
Detailed schedules are developed for which of the following?
- A) Doers and lower level control
- B) Doers and management
- C) Management and planners
- D) Planners and lower level control
Scope defines the size of the project. Scope include(s) which of the following(s)?
- A) All of the above
- B) Departments
- C) Deliverables
- D) Geographic locations
Scope change control includes
- A) None of the above
- B) Get approval from all stakeholders
- C) Get approval from all stakeholders
- D) Manage scope change requests
Which of the following methods breaks work down into system & major sub systems?
- A) Logic flow diagram
- B) Life cycle Method
- C) Flow Method
- D) Organization Method
The time differential between the scheduled completion date and required date to meet critical path is said to be
- A) Critical time
- B) None of the above
- C) Slack time
- D) Both a and b
Which of the following is a Master production schedule?
- A) Production plan
- B) Manufacturing plan
- C) Sales plan
- D) Financial plan
Scope management is mainly concerned with which of the following(s)
- A) None f the above
- B) Controlling the scope of a project
- C) Both a and b
- D) Defining the scope of a project
Contract Work Breakdown Structure (CWBS) included in Contract should not extend lower than _____________ level.
- A) Third Level
- B) Second Level
- C) Fourth Level
- D) First Level
Work Breakdown Structure (WBS) should satisfy:
- A) Functional & Program requirements
- B) Functional requirements
- C) Functional & non-functional requirements
- D) Program requirements
Uncontrolled changes in a project’s scope are called
- A) Kitchen Sink Syndrome
- B) Scope Creep
- C) Requirement creep
- D) All of the above
Which of the following is a use of Work breakdown structure?
- A) Risk cost control
- B) Cost control standard
- C) Work project
- D) Reporting
Who among the following is responsible to verify all activities of a project?
- A) Finance office
- B) Management office
- C) Functional office
- D) Program office
Which of the following items involves the quantitative aspects of planning?
- A) Leadership styles
- B) Project administration
- C) Budget development
- D) Conflict management
For scheduling the projects, Networks have the following type(s)
- A) Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM)
- B) All of the above
- C) Graphical Evaluation and Review Technique (GERT)
- D) Precedence Diagram Method (PDM)
Which of the following is the purpose of configuration management?
- A) Insure that drawings are updated
- B) Control change during production only
- C) Generate engineering change proposals
- D) Control change throughout the project
The process which is carried out whenever one or more deliverables are ready to be handed over
- A) Scope verification
- B) Scope Change Control
- C) None of the above
- D) Both a and b
The common scheduling techniques for projects are
- A) Gantt or bar charts and Milestone charts
- B) Line of balance
- C) All of the above
- D) Networks
Slack time will have which of the following(s) value when calculated on critical path activity
- A) Both a and b can happen
- B) None zero
- C) Zero
- D) None of the above