If project nature is complex, multiple teams are on board and different resource groups are acting then you should do _____________ and it is absolutely mandatory.
- A) Resource planning
- B) Designer activities
- C) Process activities
- D) Scope definition
Place all activities in an order is called ___________.
- A) Scope definition
- B) Activity definition
- C) Activity sequencing
- D) Scope planning
Evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards. Choose suitable name of this activity.
- A) Information Distribution
- B) Team Development
- C) Project Plan Execution
- D) Quality Assurance
We use _____________ when there is a conflict in client requirements.
- A) Spiral model
- B) Waterfall model
- C) Prototyping model
- D) RAD model
Every _______________has skills and knowledge that may be useful in developing the project plan.
- A) Tester
- B) Stakeholder
- C) Manager
- D) Developer
___________ (s)are tangible results produced by processes in the system, such as products or
services for consumers.
- A) Feedback
- B) Process
- C) Input
- D) Output
It is the ______________responsibility to select the structure best suited for the project.
- A) Planner
- B) Project Manager's
- C) Process Manager's
- D) Product Manager's
These are Software engineering layers except
- A) Tools
- B) Methods
- C) Process
- D) Design
During project __________, you identify the resources required and allocate them to the software project.
- A) Planning
- B) Scope
- C) Initiation
- D) Development
The _______ of scope planning are the scope statement and scope management plan, with the supporting detail.
- A) Logs
- B) Inputs
- C) processes
- D) Outputs
________ ensures that appropriate steps to follow the product development procedures are carried out
- A) Design
- B) Process monitoring
- C) Quality Management
- D) Quality control
All of the following are descriptions of how new system is to be developed in Technical Approach EXCPET ________ .
- A) Consultants
- B) Derivatives of existing
- C) Architectural Layout
- D) Technologies
Putting all logical activities together is called ___________.
- A) Developer activities
- B) Designer activities
- C) Process activities
- D) Scope planning
When you build a product or system, it's important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called a __________
- A) Software schedule
- B) Software process
- C) Framework
- D) Software design
SDP Stands for ________________.
- A) Software Defining Phase
- B) Software Development Plan
- C) Software Demanding Plan
- D) Software Design Plan
There should not be any ambiguity and any grey area in complete wording regarding the scope.
- A) Similarity planning
- B) Activity sequence
- C) Scope definition
- D) Activity definition
If the size of a project is extensive and the client prefers all the features of the proposed
project at the first delivery, you can select the ___________ Model.
- A) RAD
- B) Incremental
- C) Prototyping
- D) WaterFall
There cannot be a sudden crossover from one phase to the next in __________.
- A) RAD model
- B) Spiral model
- C) Prototyping model
- D) Waterfall model
People are managed through a(n) _______ .
- A) Organizational culture
- B) Nature
- C) Organizational structure
- D) Culture
An output from the quality planning process is
- A) Quality management plan
- B) Acceptance decision
- C) Process adjustment
- D) Quality improvements