MCQ Bank
Inspection costs, belong to which of the following?
- A) Appraisal costs
- B) External failure costs
- C) Prevention costs
- D) Internal failure costs
Empowerment, encourages which of the following?
- A) Responsibility
- B) Innovation
- C) Motivation
- D) Authority
Root Cause Analysis, relates to which of the following?
- A) Quality audits
- B) Process analysis
- C) Performance measurements
- D) Quality control measurements
Which of the following is NOT a conformance cost?
- A) Validation
- B) Verification
- C) Testing
- D) Rework
Which of the following is the source of product and process requirement?
- A) Intermediary
- B) Primary customer
- C) External customer
- D) Secondary customer
_______________ gives little practical approach to managers.
- A) Product-based criteria
- B) User-based criteria
- C) Integrating perspectives on quality
- D) Judgmental criteria
Which of the following cost estimation is more time consuming?
- A) Overhead
- B) Labor cost
- C) Material cost
- D) Indirect cost
A Pareto diagram, can be best described as which of the following?
- A) Control chart
- B) Histogram
- C) Cause-and-effect diagram
- D) Scatter chart
The project manager has the greatest impact on the quality of the product at _______________ stage.
- A) Quality assurance
- B) Quality management
- C) Total Quality Management
- D) Inspection
____________ is the balance between quality and cost.
- A) Salability
- B) Operability
- C) Reliability
- D) Maintainability
________________ results in users' satisfaction.
- A) Value
- B) Rules
- C) Product/service
- D) Quality
Which of the following is not a characteristic of project organization?
- A) Quality
- B) Distinct purpose
- C) Systematic structure
- D) People
Quality is defined by_____________.
- A) Quality management
- B) Higher management
- C) Customer
- D) Proposal manager
Which of the following criterias offers greater satisfaction at comparable price?
- A) Judgmental criteria
- B) Product-based criteria
- C) Value-based criteria
- D) Integrating perspectives on quality
Lack of ownership exists at _____________ level.
- A) Quality Management
- B) Quality Control
- C) Inspection
- D) Quality Assurance
Which of the following have NO relative impact on price level?
- A) Life-cycle cost
- B) Bidder’s cost estimate
- C) Customer budget
- D) Competitive prices
What is quality dimension development?
- A) The customer defection
- B) The customer retention
- C) The method of measuring customer satisfaction
- D) The customer satisfaction system
Process Analysis, is a function of which of the following?
- A) Quality Improvement Plan
- B) Performance Analysis
- C) Quality Metrics
- D) Process Improvement Plan
Which of the following companies have tighter monetary control?
- A) Large companies
- B) Non profit oriented companies
- C) Profit oriented companies
- D) Small companies
_____________ is the other name of project pricing model.
- A) Project model
- B) Strategic planning model
- C) Strategic project planning model
- D) Planning model