Cycle time for the economic run size is a function of which of the following?
- A) Run time and usage rate
- B) Run time and production rate
- C) Run size and production rate
- D) Run size and usage rate
Which of the following is a computerized info system developed specifically to aid in managing dependent demand inventory and scheduling replenishment orders.
- A) Material Requirements Planning
- B) Master Production Schedule
- C) Inventory Management Schedule
- D) Material Replenishment Planning
Which of the following refers to the costs incurred to get the equipment ready for the next job?
- A) Ordering cost
- B) Holding cost
- C) Setup cost
- D) Shortage cost
To meet JIT objectives, the process relies on ________between different points in the process.
- A) JIT planning
- B) Signals or kanban
- C) Continuous improvement
- D) Variability increase
Under which of the following, the lot size order covers the gross requirements of a single week?
- A) Economic order quantity model
- B) Part period model
- C) Lot for lot ordering
- D) Fixed period ordering
Planning is much easier and flexible in which of the following?
- A) Production
- B) Research and development
- C) Manufacturing
- D) Services
Which of the following denotes EOQ?
- A) Economic Output Quantity
- B) Equal Order Quantity
- C) Economic Order Quantity
- D) Equal Output Quantity
“Minimize resources needed for Design and Manufacturing” This statement can be categorized among the goals of:
- A) Employee motivation
- B) Re engineering
- C) JIT system
- D) Strategic Manufacturing
Lot sizing technique that produces exactly what was required to meet the plan is
- A) Bills of materials
- B) Lot for lot
- C) EOQ
- D) Part period balancing
Which of the following is the cost of holding inventory for some specific time?
- A) Shrinkage cost
- B) Ordering cost
- C) Carrying cost
- D) Inventory cost
Which one of the following is an example of a short range plan?
- A) Facilities layout
- B) Back order
- C) Product design
- D) Machine loading
Which of the following time fences in a Master Production Schedule (MPS) allows many variations in products with multiple changes?
- A) Moderately firm time fence
- B) Fixed time fence
- C) Flexible time fence
- D) Frozen time fence
JIT is a philosophy of continuous improvement that puts emphasis on prevention rather than:
- A) All of the given
- B) Correction
- C) Employee motivation
- D) Manufacturing
Which of the following shows the quality and timing of specific end items for a scheduled horizon?
- A) Aggregate plan
- B) Simulation model
- C) Critical path model
- D) Master schedule
The main elements of JIT comprises of:
- A) Continuous improvement
- B) Set-up time reduction
- C) Eliminating waste
- D) All of the given
Changes made in ____ phase of MPS can be most disruptive
- A) 3rd
- B) 4th
- C) 2nd
- D) 1st
Which of the following is a benefit of ERP?
- A) ERP is very inexpensive to purchase
- B) ERP creates commonality of databases
- C) ERP requires major changes to the company and its processes
- D) ERP is simple enough that companies have an easy time adjusting to it
Which one of the following is a formula to compute annual carrying cost?
- A) (Q+2)H
- B) (Q-2)H
- C) (Q/2)H
- D) (Q×2)/H
Which of the following is one of the two relevant costs in Economic Order Quantity Model?
- A) Annual inventory holding cost
- B) Opportunity cost
- C) Shrinkage cost
- D) Shortage costs
For production plans, the demand requirement represents the demand for _________________?
- A) Inventory
- B) Finished goods
- C) Work in process
- D) Raw material