MCQ Bank
A project is considered as……………. if the cash flows of one are unaffected by the acceptance of the other.
- A) Mutually exclusive
- B) Independent
- C) Dependent
- D) Acceptable
Which of the following capital budgeting techniques provides that value of an asset today is equal to sum of present values of future cash flows?
- A) Internal rate of return
- B) Profitability index
- C) Net present value
- D) Payback period
Following information for certain period has been extracted from the books of a manufacturing concern to find the value of Operating Cash flow.
Net Profit before tax: Rs. 793,600; tax rate: 35% and depreciation: Rs. 500,000
- A) Rs. 500,000
- B) Rs. 550,840
- C) Rs. 550,840
- D) Rs. 1,015,840
Actual hours worked= 4,000
Standard labor rate=180 Rs. Per hour
Actual labor rate= 200 Rs. Per hour
Labor rate variance= ?
- A) Rs. 80,000 Favorable
- B) Rs. 800,000 Adverse
- C) Rs. 800,000 Favorable
- D) Rs. 80,000 Adverse
Sales price per unit= Rs.30.50
Variable cost per unit=Rs.12.50
Contribution to sales ratio= ?
- A) .65
- B) .59
- C) .15
- D) .45
Which of the following is a vital role of variance analysis in decision making?
- A) All of the given options
- B) To analyze the total variance into elements
- C) To take corrective actions
- D) To establish responsibility
Under standard costing what will be done if actual varies favorably or unfavorably from the standards?
- A) All of the given options
- B) Analysis of variance
- C) Reporting of variance
- D) Investigation of variance
Fixed costs of XYZ company was of Rs. 5,500, and sold 30 units for Rs. 140 each. The total variable costs were Rs. 1,600. What is the net income or loss of the Company?
- A) Rs. 2,900 loss
- B) Rs. 2,600 loss
- C) Rs. 2,600 profit
- D) Rs. 2,900 profit
Following information has been extracted from the books of Ali & Co to calculate the contribution sales ratio.
Sales price per unit Rs. 20
Variable cost per unit Rs. 15
- A) 0.75
- B) 35.00
- C) 5.00
- D) 0.25
Sales price per unit= Rs.80,000
Units sold= 1000 units
Variable cost per unit=Rs.68
Contribution margin= ?
- A) Rs.80,000
- B) Rs.120,000
- C) Rs.68,000
- D) Rs.800,000
Sales value of product D after further processing is of Rs. 19,000; sales value of the product at split off is of Rs. 15,000; and additional processing cost of Rs. 5,000.
Required: At what point Product D should sale and why?
- A) Further processing on product D causes higher incremental sales revenue in this case
- B) It should be sold at split off point because additional processing cost is higher than incremental sales revenue.
- C) More information is required to identify the reason
- D) It should be sold at split off point because additional processing cost is lesser than incremental costs.
Absorbed variable overhead= Rs. 300,000
Standard variable overhead= Rs. 360,000
Budgeted factory overhead= Rs. 12,00,000
Actual factory overhead= Rs. 11,60,000
Variable overhead efficiency variance= ?
- A) Rs. 60,000 Adverse
- B) Rs. 40,000 Adverse
- C) Rs. 40,000 Favorable
- D) Rs. 60,000 Favorable
An electric company produced and sold ceiling fans at Rs. 1,600 each by incurring the variable cost of Rs. 1,200 each and fixed cost of Rs. 300,000.
Required: What is contribution margin per unit?
- A) Rs.400
- B) Rs.200
- C) Rs.280
- D) Rs.300
Identify Sales Volume Profit Variance if actual units sold and budgeted sold units are 35,000 units and 45,000 units respectively. Actual sales price per unit, standard profit per unit and standard sales price per unit are Rs. 215, Rs. 39 and Rs. 205 respectively.
- A) Rs. 390,000 adverse
- B) Rs. 350,000 adverse
- C) Rs. 390,000 favorable
- D) Rs. 350,000 favorable
Actual material used= 7,000 units
Standard material usage= 8,000 units
Standard cost of maerial= 40.4 Rs. Per unit
Material usage variance= ?
- A) Rs. 1,000 Adverse
- B) Rs. 44,400 Favorable
- C) Rs. 1,000 Favorable
- D) Rs. 44,400 Adverse
Which of the following is fixed overhead variance?
- A) Efficiency variance
- B) Spending variance
- C) Volume variance
- D) None of the given options
Actual labor hours= 150,000
Standard labor hours= 165,000
Standard labor rate= 15 Rs. Per hour
Actual labor rate= 17 Rs. Per hour
Labor efficiency variance= ?
- A) Rs. 225,000 Adverse
- B) Rs. 225,000 Favorable
- C) Rs. 240,000 Adverse
- D) Rs. 240,000 Favorable
Actual hours worked= 4,400
Standard labor rate= 240 Rs. Per hour
Actual labor rate= 200 Rs. Per hour
Labor rate variance= ?
- A) Rs. 88,000 Favorable
- B) Rs. 88,000 Adverse
- C) Rs. 176,000 Favorable
- D) Rs. 176,000 Adverse
An electric company produced and sold ceiling fans at Rs. 1,600 each by incurring the variable cost of Rs. 1,200 each and fixed cost of Rs. 300,000.
Required: What is contribution margin ratio?
- A) 0.30
- B) 0.12
- C) 0.25
- D) 0.16
Following information has been extracted from ABC Company.
Actual cost incurred Rs. 39,000; Budget based on actual activity Rs. 38,000 and Standard Cost of actual output Rs. 39,500.
Required: Identify Spending Variance with the help of provided information.
- A) Rs. 1,500 adverse
- B) Rs. 1,000 favorable
- C) Rs. 1,500 favorable
- D) Rs. 1,000 adverse